Boulder Highway is more than 71% complete, and construction is still affecting trips through eastern Henderson. At the October 14 State of the City address, Mayor Michelle Romero said the project remains on schedule for an August 2027 finish.
That timeline matters to drivers, bus riders, nearby businesses and anyone crossing the corridor on foot. The address also outlined Henderson’s priorities for the coming years, including attainable housing, schools, public safety and parks.
Here’s what residents can use now—and what is still in progress.
Boulder Highway: current work and what’s planned
The Reimagine Boulder Highway project covers 7.5 miles between Tulip Falls Drive and Wagonwheel Drive. It combines roadway work with drainage, lighting, safer crossings, bike facilities and center-running bus rapid transit.
At the October address, the mayor reported nearly 20,000 feet of underground storm drains installed, signal upgrades at 17 intersections and nearly 400 new streetlights activated. Center islands are also being built to give pedestrians a place to pause while crossing.
The project schedule lists August 2027, while the FAQ says construction is anticipated through July 2027. The site says its schedule is subject to change. Before traveling, check the latest segment updates; lane access, bus stops and work hours can differ by location.
Henderson’s other priorities, in practical terms
The mayor’s 2026 State of the City address covered several initiatives that could affect household choices and neighborhood services:
These projects are at different stages. A land transfer, construction estimate or planned opening is a milestone—not a guarantee that a home, school program or recreation service is available today.
How to follow changes that affect you
For a commute or visit along Boulder Highway, use the project’s construction updates for segment-level work and bus-stop changes. You can sign up for alerts on its Stay Informed page.
For housing, schools, parks and city services, check the relevant city department or State of the City page for later announcements. Look for confirmed dates, access changes, eligibility rules and application windows that apply to your neighborhood.
As of the October 14, 2026 address, these were projects and goals reported by city officials. Timelines and plans may change. |
![]() AI-generated illustration of Boulder Highway Construction; not an actual photograph. Illustration: Henderson Shoutouts. |
Henderson’s plans are easiest to understand when you look for the next practical milestone: a confirmed construction schedule, a home’s application date, a school enrollment window or a recreation center’s opening details.
For Boulder Highway, those changes can be immediate. Temporary access and transit arrangements may shift as crews move between segments, even while the broader project aims to improve safety and mobility.
The city’s other priorities will unfold more gradually. Residents can follow the city’s updates and each project’s own notices to see when plans become services people can use.
For now, check the latest official notice before making a trip or planning around a projected opening. |



9 Comments
Join the conversation
The upgraded signals at 17 intersections sound promising, though I'd like to know how the city will tell whether crossings are actually safer afterward.
Jill B.I'd like to see crash numbers before and after, plus whether people have enough time to cross near the bus stops.
That’s an important question. The city has reported the signal upgrades and new pedestrian islands, but we haven’t seen a published plan for measuring crossing safety after construction. We’ll watch for one.
Nearly 20,000 feet of storm drains is a lot of work people won't see once it's covered. Glad that's part of the rebuild.
Omar PatelAgreed. If those drains keep water from pooling during summer storms, the work will be worth it.
As someone who plans errands around bus routes, the transit part matters to me. I hope the new stops have shade when the work is done.
Does anyone know where to check bus stop changes for each stretch of Boulder Highway? That would help people plan before heading out.
Seventy one percent complete sounds good, but July 2027 is still a long way off. I hope nearby businesses can keep their entrances easy to find.
The center islands sound like a useful safety change on Boulder Highway. Will the pedestrian detours stay clearly marked while construction moves between segments?